Bellsbank Plant Construction
1 - Historical infrastructure inherited (Jan 2005)
2 - Crane dismantling old plant (Jan 2006)
3 - Salvage of steel and motors/drivers (Jan 2006)
4 - Construction of level 1 decking
5 - Pan construction and fabrication
6 - Pan construction and fabrication
7 - Level 1 Diamond recovery pan base installation (March 2006)
8 - Construction of level 2 decking (March 2006)
9 - Delivery of mill to site (March 2006)
10 - Fabrication of ore bins and tanks (April 2006)
11 - Mill plinth fabrication (April 2006)
12 - Refurbishment of screens and conveyors (April 2006)
13 - Refurbishment of screens and conveyors (April 2006)
14 - Tailings hopper refurbishment (April 2006)
15 - Level 2 deck development (April 2006)
16 - Level 2 deck cladding (April 2006)
17 - Overview of plant site refurbishment
18 - Screen and conveyor upgrades
19 - Inside view of the new plant during construction
20 - Outer cladding near completion
21 - Conveyor refurbishment
22 - Pumps delivered to site
23 - Internal view of level 3 deck
24 - Screen installation
25 - Substation under construction
26 - Main plant installation continuing on schedule
27 - Continuing to refurbish conveyor system
28 - Rust proofing and sandblasting of mill prior to installation
29 - Installation of the mill
30 - Main plant and final recovery section with new 100 tonne tailings feed bin installed
31 - Tailings conveyor and screen installed in main plant