Bellsbank Plant Construction

1 - Historical infrastructure inherited (Jan 2005)

2 - Crane dismantling old plant (Jan 2006)


3 - Salvage of steel and motors/drivers (Jan 2006)

4 - Construction of level 1 decking


5 - Pan construction and fabrication

6 - Pan construction and fabrication


7 - Level 1 Diamond recovery pan base installation (March 2006)

8 - Construction of level 2 decking (March 2006)


9 - Delivery of mill to site (March 2006)

10 - Fabrication of ore bins and tanks (April 2006)


11 - Mill plinth fabrication (April 2006)

12 - Refurbishment of screens and conveyors (April 2006)


13 - Refurbishment of screens and conveyors (April 2006)

14 - Tailings hopper refurbishment (April 2006)


15 - Level 2 deck development (April 2006)

16 - Level 2 deck cladding (April 2006)


17 - Overview of plant site refurbishment

18 - Screen and conveyor upgrades


19 - Inside view of the new plant during construction

20 - Outer cladding near completion


21 - Conveyor refurbishment

22 - Pumps delivered to site


23 - Internal view of level 3 deck

24 - Screen installation


25 - Substation under construction

26 - Main plant installation continuing on schedule


27 - Continuing to refurbish conveyor system

28 - Rust proofing and sandblasting of mill prior to installation


29 - Installation of the mill

30 - Main plant and final recovery section with new 100 tonne tailings feed bin installed


31 - Tailings conveyor and screen installed in main plant

32 - Ore feed conveyor and oversize return conveyor